Deck crane load testing and job close-out

SVC Marine coordinated a scheduled five-year crane load-test attendance. The job correspondence continued through the work-done report, final invoice and payment follow-up.

Case study

Service
Crane load-test attendance
Scope
Scheduled five-year crane load testing
Close-out
Work-done report and final invoice
Published

The scheduled crane attendance

The vessel's enquiry concerned its scheduled five-year crane load testing. SVC Marine handled the service correspondence and followed the attendance through to the work-done report and commercial close-out.

For this kind of attendance, the enquiry needs to identify the actual lifting appliances and the required test scope. A deck crane, provision crane and engine-room lifting appliance may have different capacities, access arrangements and documentation requirements.

The work-done report and close-out

After the attendance, SVC Marine forwarded the work-done report and final invoice. The correspondence also covered an additional job invoice and subsequent payment follow-up.

A useful close-out connects the requested work with the attendance record. Test readings, certificate requirements and any additional work should be identified for the particular appliance and agreed scope.

Preparing a crane load-test enquiry

Send the crane maker, model, identification number and safe working load, together with the reason for testing and the previous report or certificate. Identify any repair or equipment change that needs to be considered when defining the attendance.

Provide the port or anchorage, ETA, available working window and onboard access arrangements. Clarify the required test equipment and whether an owner's representative, superintendent or surveyor needs to attend.

  • Crane identification, maker/model and safe working load
  • Requested test scope and previous report or certificate
  • Port or anchorage, ETA and available working window
  • Access, equipment handling and required witness arrangements
Water-bag load-test arrangement on a deck crane
Water-bag load-test arrangement on a deck crane.

Arrange crane service attendance

Contact [email protected] for crane load-test and related technical attendance at Vietnamese ports. SVC Marine can review the enquiry, define the requested service and coordinate the attendance and reporting requirements with the vessel's team.

Talk to SVC Marine

Please provide your company details and the vessel requirement or work scope. Acceptance is subject to verification and confirmation by SVC Marine.