CO2 Pipe System Renewal at Chan May Port, Vietnam
Published
SVC’s pipe fitters and welders renewed damaged CO2 pipe sections on board at Chan May Port. The job took 3/4-inch t3 steel pipes from the workshop to the vessel, then through removal, bending, fitting, welding, U-bolt installation, NDT checks and painting.
The Chan May record shows the completed pipe renewal. For a new fixed CO2 system enquiry, SVC prepares the appointed pipe worklist with the vessel’s responsible officers, including access, safe isolation, fabrication, inspection points and the required tests before the system returns to service.
Work packages
- 3/4-inch steel pipes prepared at the workshop
- Damaged sections removed on board
- New pipes fitted, bent and welded
- U-bolts installed; NDT and painting completed





01
Prepare pipes for the Chan May job
The work started with replacement steel pipes and the vessel’s damaged CO2 sections. SVC prepared the 3/4-inch t3 steel pipes at the workshop and transferred them to Chan May Port for the onboard renewal. The material reference belongs to this job; a different repair uses its own drawing and specified pipe size.
Our team inspected the damaged sections onboard and identified the renewal areas. Workshop preparation and material transfer were part of the same worklist, so the pipe fitters and welders could proceed when the vessel made the work area available.
02
Remove, bend, fit and weld the new sections
Our team removed the damaged CO2 pipes, prepared the new sections and bent them to the required route. The pipe fitters assembled the new sections; our welders completed the appointed joints. U-bolts and the pipe mounting points were installed to hold the renewed sections in position.
The Chan May work sequence covered material transfer, inspection, removal, preparation, bending, fitting, welding, U-bolt installation, inspection and finishing. The original photographs show the condition before renewal and the replacement work onboard.
03
NDT checks and finishing on the job
The recorded work included NDT checking of the renewed pipe joints where required, surface preparation and painting after the renewal. SVC recorded the replacement areas and finished condition as part of the repair.
This job’s inspection record covers the NDT and finishing described above. For another renewal, choose leak, pressure or blowing tests against the affected system and repair before work starts.
04
Why fixed CO2 pipe condition matters
CO2 pipes deliver the extinguishing agent to the protected spaces. Holes, corrosion, loose sections, obstructions or disconnected branches can affect delivery in an emergency. Inspect the complete affected run, fittings and nozzles instead of treating a visible rusty patch as the only item.
SVC carries out the commissioned pipe renewal for commercial ships, including bulk carriers, general cargo and container vessels, tankers, MPP and offshore vessels, tugboats and workboats. Pipe condition may require attention during annual fire-system checks, drydock, class or port-state inspections.
- External corrosion, paint breakdown and rust formation.
- Wasted pipe wall, visible holes or leaking joints.
- Missing or damaged U-bolts, clamps, brackets or hangers.
- Loose or vibrating pipe sections.
- Blocked or contaminated lines, damaged nozzles or branch lines.
- Inspection or survey comments identifying defects in the fixed fire-extinguishing system.
05
Define the renewal worklist
The extent of a CO2 pipe renewal depends on pipe size and wall specification, damaged length, connection points, route, access, system layout, inspection requirements and the vessel’s available working window. Mark the defective sections before quoting quantities.
- Inspect the damaged or corroded run and check pipe size, route, mounting points and connections.
- Mark the removal boundaries; remove the appointed old pipes, clamps, brackets or damaged fittings.
- Fabricate the new sections at the workshop or onboard against the agreed drawing and dimensions.
- Cut, bend, thread and fit the pipe, or prepare flange connections where the design requires them.
- Carry out the commissioned onboard welding with SVC marine welders.
- Install U-bolts, clamps and pipe mounting points; check route and clearances.
- Perform the agreed NDT, leak, pressure or blowing checks as applicable.
- Prepare the surfaces, apply primer and paint, and record the finished work.
06
Fabricate, bend and weld
Our pipe fitters prepare the route and fit-up so new sections connect correctly to the retained system. Bending, threaded or flanged joints and welded connections use the vessel’s specified arrangement. Our welders carry out the appointed welds; the worklist identifies the inspection points before finishing.
Access, clean fit-up, correct routing, adequate mounting and the agreed welding quality matter throughout the job. State the drawing revision, pipe specification and joint details before fabrication. Identify any damaged connection or bracket that needs renewal along with the pipe.
SVC’s wider pipe work includes CO2 and fire-main lines, sea-water, ballast, bilge, air and deck-service pipes, hydraulic lines and engine-room pipe renewal. Pipe clamps, brackets and hangers can be included in the same enquiry. Keep each system’s material, isolation and test requirements distinct.
07
Agree inspection and testing before work
The vessel’s system requirements, repair location and Surveyor’s instructions determine the inspection and test plan. Agree the method before starting so the technicians can prepare the joints, access, test boundaries and witnessing points. A pressure test, leak check and blowing-through check answer different questions.
- Visual inspection of the renewed sections and joint fit-up.
- Dye-penetrant testing or other specified NDT where required.
- Leak or pressure testing where applicable to the appointed repair.
- Blowing through CO2 lines where required for the system.
- Checks of U-bolts, clamps, brackets, route and clearances.
- Surface preparation, primer and painting after the required inspections.
- Final photographs, test results, outstanding items and the completion report.
08
Safe work on a fixed CO2 system
Only start removal, cutting or welding after the vessel’s responsible officers have confirmed that the affected system and work area are made safe and isolated as required. Discuss the protected spaces, cylinder-bank condition and release controls before attendance.
The work plan covers hot-work permission, ventilation, fire watch, access and the precautions for the affected fire-protection system. Preserve the release arrangements and safety interlocks. Pipe repair must not inadvertently discharge CO2 or compromise the fire-protection function.
After the appointed renewal and tests, record the condition of the affected system before return to normal service. Apply the relevant class, flag, fire-safety service or Surveyor’s requirements for the particular vessel; inspection acceptance is not automatically created by completing a weld.
09
When to request inspection or renewal
Send a worklist when pipe wall wastage, visible corrosion, leakage, holes, damaged brackets or a suspected blockage is found. Include any class, Surveyor or port-state comment so the repair addresses the specific deficiency.
Annual fire-system inspection and drydock can provide a planned work window. A damaged fire-fighting line may need a different attendance plan during an afloat port call. Identify the current operating restriction, available access and required completion time with the vessel’s responsible officers.
10
CO2 pipe repair at Chan May and Vietnam ports
SVC provides pipe fabrication, onboard welding, inspection attendance and appointed ship repairs at selected Vietnamese ports, shipyards and anchorages. Enquiry locations include Chan May, Da Nang, Dung Quat, Quy Nhon, Vung Ang, Son Duong, Hon La, Cua Lo, Nghi Son, Hai Phong, Hon Gai, Cam Pha, Cai Lan, Vung Tau, Phu My, Cai Mep, the Ho Chi Minh City area, Long An and Vinh Tan. Confirm the actual terminal, boarding and work window in the quotation.
For the central-port worklist, see ship repair at Da Nang, ship repair at Dung Quat and Vung Ang/Son Duong repair. Ship repair in Vietnam covers related machinery, electrical and hydraulic work. The marine pipe renewal service addresses wider piping enquiries.
11
Send the pipe defect and work window
Send the CO2 pipe worklist with the following particulars through SVC’s private repair contact:
- Vessel reference, vessel type and the exact port, terminal or anchorage.
- ETA/ETD and the available inspection and repair window.
- Photographs showing the defect, joints, route, nozzles and mounting points.
- Pipe size and specified wall/material particulars, damaged location and estimated renewal length.
- The relevant piping drawing, connection details and drawing revision, where available.
- Class, Surveyor or fire-safety requirements, including the proposed inspection and testing.
- Access restrictions, isolation arrangements and whether workshop preparation is possible before attendance.
12
CO2 pipe repair questions
Does SVC renew fixed CO2 pipes in Vietnam?
Yes. Our pipe fitters and welders carry out the appointed steel-pipe fabrication, bending, fitting and welding, with U-bolts and mounting points, agreed inspection and painting. The Chan May case records one completed renewal; a new worklist is defined against the affected vessel’s system.
When should CO2 pipes be renewed?
Request inspection when pipes are corroded, wasted, holed, leaking, damaged, loose or inadequately mounted, or where a fire-system, class or port-state inspection identifies a defect. The responsible officers and applicable technical requirements determine the renewal boundaries and return-to-service checks.
Can SVC fabricate and weld pipes onboard?
Our team can prepare, bend, fit and weld the appointed pipe sections onboard or at the workshop. The selected method depends on pipe size, connection details, access, safe isolation, hot-work permission and the vessel’s schedule.
What tests are needed after renewal?
Agree the test plan for the particular system and repair before work starts. It may include visual inspection, specified NDT, leak or pressure testing, blowing through and the relevant final checks. The completion report records the tests actually performed and the results.
What should an owner send for a quotation?
Send the vessel reference privately, exact port or anchorage, ETA and working window, photographs, pipe size and material, defect location, estimated renewal length and the drawing if available. Include the class or fire-safety requirements and access or isolation constraints.